REVENUE, CONTRACT ASSETS AND LIABILITIES AND OTHER CONTRACT MATTERS |
2. REVENUE, CONTRACT ASSETS AND LIABILITIES AND OTHER CONTRACT MATTERS
As discussed in Note 1, we recognize revenue for our contracts in accordance with Topic 606. Summarized below are required disclosures under Topic 606 and other relevant guidance.
Disaggregation of Revenue
The following tables summarize revenue for each of our operating segments, disaggregated by contract type, for 2020, 2019 and 2018 (in thousands):
|
|
Year Ended December 31, 2020
|
|
Contract Type
|
|
Shipyard
|
|
|
F&S
|
|
|
Eliminations
|
|
|
Total
|
|
Fixed-price and unit-rate (1)
|
|
$
|
151,508
|
|
|
$
|
66,790
|
|
|
$
|
(148
|
)
|
|
$
|
218,150
|
|
T&M (2)
|
|
|
2,190
|
|
|
|
25,294
|
|
|
|
(388
|
)
|
|
|
27,096
|
|
Other
|
|
|
—
|
|
|
|
7,401
|
|
|
|
(1,688
|
)
|
|
|
5,713
|
|
Total
|
|
$
|
153,698
|
|
|
$
|
99,485
|
|
|
$
|
(2,224
|
)
|
|
$
|
250,959
|
|
|
|
Year Ended December 31, 2019 (3)
|
|
Contract Type
|
|
Shipyard
|
|
|
F&S
|
|
|
Eliminations
|
|
|
Total
|
|
Fixed-price and unit-rate (1)
|
|
$
|
161,839
|
|
|
$
|
86,211
|
|
|
$
|
(430
|
)
|
|
$
|
247,620
|
|
T&M (2)
|
|
|
6,627
|
|
|
|
41,014
|
|
|
|
—
|
|
|
|
47,641
|
|
Other
|
|
|
—
|
|
|
|
9,944
|
|
|
|
(1,897
|
)
|
|
|
8,047
|
|
Total
|
|
$
|
168,466
|
|
|
$
|
137,169
|
|
|
$
|
(2,327
|
)
|
|
$
|
303,308
|
|
|
|
Year Ended December 31, 2018 (3)
|
|
Contract Type
|
|
Shipyard
|
|
|
F&S
|
|
|
Eliminations
|
|
|
Total
|
|
Fixed-price and unit-rate (1)
|
|
$
|
88,887
|
|
|
$
|
77,318
|
|
|
$
|
(700
|
)
|
|
$
|
165,505
|
|
T&M (2)
|
|
|
7,537
|
|
|
|
43,481
|
|
|
|
—
|
|
|
|
51,018
|
|
Other
|
|
|
—
|
|
|
|
5,896
|
|
|
|
(1,172
|
)
|
|
|
4,724
|
|
Total
|
|
$
|
96,424
|
|
|
$
|
126,695
|
|
|
$
|
(1,872
|
)
|
|
$
|
221,247
|
|
|
(1)
|
Revenue is recognized as the contract is progressed over time.
|
|
(2)
|
Revenue is recognized at contracted rates when the work is performed and costs are incurred.
|
|
(3)
|
See Note 10 for discussion of our realigned operating divisions.
|
Future Performance Obligations Required Under Contracts
The following table summarizes our remaining performance obligations by operating segment at December 31, 2020 (in thousands).
Segment
|
|
Performance
Obligations
|
|
Shipyard
|
|
$
|
352,181
|
|
F&S
|
|
|
19,381
|
|
Total
|
|
$
|
371,562
|
|
We expect to recognize revenue for our remaining performance obligations at December 31, 2020, in the following periods (in thousands):
Year
|
|
Total
|
|
2021
|
|
$
|
161,370
|
|
2022
|
|
|
140,018
|
|
2022 and beyond
|
|
|
70,174
|
|
Total
|
|
$
|
371,562
|
|
Contracts Assets and Liabilities
Revenue recognition and customer invoicing for our fixed-price and unit-rate contracts may occur at different times. Revenue recognition is based upon our estimated percentage-of-completion as discussed in Note 1; however, customer invoicing is generally dependent upon predetermined billing terms, which could provide for customer payments in advance of performing the work, milestone billings based on the completion of certain phases of the work, or billings when services are provided. Revenue recognized in excess of amounts billed is reflected as contract assets on our Balance Sheet. Amounts billed in excess of revenue recognized, and accrued contract losses, are reflected as contract liabilities on our Balance Sheet. Information with respect to uncompleted contracts at December 31, 2020 and 2019 is as follows (in thousands):
|
|
December 31,
|
|
|
|
2020
|
|
|
2019
|
|
Costs incurred on uncompleted contracts
|
|
$
|
328,229
|
|
|
$
|
386,932
|
|
Estimated loss incurred to date
|
|
|
(19,617
|
)
|
|
|
(48,895
|
)
|
Sub-total
|
|
|
308,612
|
|
|
|
338,037
|
|
Billings to date
|
|
|
(256,220
|
)
|
|
|
(295,136
|
)
|
Deferred revenue (1)
|
|
|
—
|
|
|
|
(4,592
|
)
|
Total
|
|
$
|
52,392
|
|
|
$
|
38,309
|
|
The above amounts are included within the following captions on our Balance Sheet at December 31, 2020 and 2019 (in thousands):
|
|
December 31,
|
|
|
|
2020
|
|
|
2019
|
|
Contract assets (2)
|
|
$
|
67,521
|
|
|
$
|
52,128
|
|
Contract liabilities (2), (3), (4)
|
|
|
(15,129
|
)
|
|
|
(26,271
|
)
|
Sub-total
|
|
|
52,392
|
|
|
|
25,857
|
|
Contract assets, noncurrent (1)
|
|
|
—
|
|
|
|
12,452
|
|
Total
|
|
$
|
52,392
|
|
|
$
|
38,309
|
|
|
(1)
|
We have contracts for the construction of two MPSVs that are subject to purported termination by our customer. Our net contract asset, accrued contract losses and deferred revenue balances at the time of the customer’s purported terminations of the contracts totaled $12.5 million and such amount has been reflected within other noncurrent assets on our Balance Sheet at December 31, 2020 and 2019. Although the net contract asset of $12.5 million was included within other noncurrent assets on our Balance Sheet at December 31, 2020, the information with respect to such contracts is not presented in the tables above at December 31, 2020 given the prolonged nature of the dispute. See Note 8 for further discussion of our MPSV contracts.
|
|
(2)
|
The increase in contract assets compared to December 31, 2019, was primarily due to increased unbilled positions on three projects in our Shipyard Division, offset partially by decreased unbilled positions on four projects in our Shipyard Division and a project in our Fabrication & Services Division. The decrease in contract liabilities compared to December 31, 2019, was primarily due to the unwind of advance payments on two projects in our Shipyard Division and two projects in our Fabrication & Services Division, offset partially by advance payments on a project in our Shipyard Division.
|
|
(3)
|
Revenue recognized during 2020, 2019 and 2018 related to amounts included in our contract liabilities balance at December 31, 2019, 2018 and 2017, was $18.2 million, $14.3 million and $5.1 million, respectively.
|
|
|
Contract liabilities at December 31, 2020 and 2019, includes accrued contract losses of $8.6 million and $6.4 million, respectively. See “Changes in Project Estimates” below for further discussion of our accrued contract losses.
|
Significant Customers
We are not dependent on any one customer, and the revenue derived from each customer varies from year to year based on new project awards for each customer. However, for 2020, 2019 and 2018, certain customers individually accounted for 10% or more of our consolidated revenue as follows (in thousands):
|
|
Years Ended December, 31
|
|
Customer
|
|
2020
|
|
|
2019
|
|
|
2018
|
|
A
|
|
$
|
37,986
|
|
|
$
|
52,310
|
|
|
*
|
|
B
|
|
|
77,342
|
|
|
|
39,897
|
|
|
*
|
|
C
|
|
*
|
|
|
|
36,175
|
|
|
|
49,123
|
|
D
|
|
*
|
|
|
|
34,448
|
|
|
*
|
|
E
|
|
*
|
|
|
*
|
|
|
|
25,873
|
|
F
|
|
*
|
|
|
*
|
|
|
|
23,279
|
|
G
|
|
*
|
|
|
*
|
|
|
*
|
|
|
*
|
The customer revenue was less than 10% of consolidated revenue for the year.
|
Allowance for Doubtful Accounts
Our provision for bad debts is included in other (income) expense, net on our Statement of Operations. Our provision for bad debts for 2020, 2019 and 2018, and our allowance for doubtful accounts at December 31, 2020 and 2019, were not significant.
Variable Consideration
For 2019, 2018 and 2017, we had no material amounts in revenue related to unapproved change orders, claims or incentives. However, at December 31, 2020 and 2019, certain uncompleted projects reflected a reduction in contract price for liquidated damages of $0.6 million and $12.9 million, respectively, of which $11.2 million of the liquidated damages at December 31, 2019 relate to purported liquidated damages on our contracts for the construction of two MPSVs that are subject to purported notices of termination by our customer. As discussed under “Contract Assets and Liabilities” above, we had a net contract asset at December 31, 2020 and 2019, of $12.5 million (inclusive of the impact of the purported liquidated damages previously recorded) related to these contracts; however, the liquidated damages with respect to these contracts is not presented in our variable consideration disclosure at December 31, 2020. See Note 8 for further discussion of our MPSV contracts.
Changes in Project Estimates
Changes in Estimates for 2020 – For 2020, significant changes in estimated margins on projects negatively impacted operating results for our Shipyard Division by $16.6 million and positively impacted operating results for our Fabrication & Services Division by $2.7 million. The changes in estimates were associated with the following:
Shipyard Division
|
•
|
Towing, Salvage and Rescue Ship Projects – Negative impact for 2020 of $7.3 million resulting from increased forecast costs for our five towing, salvage and rescue ship projects, primarily associated with increased craft labor and subcontracted services costs and extensions of schedules. The impacts were primarily due to lower than anticipated craft labor productivity and progress on the projects and higher cost estimates for subcontracted services resulting from the current and forecasted impacts of COVID-19 associated primarily with engineering delays, increased employee and contractor absenteeism and turnover, challenges recruiting and hiring craft labor, physical distancing measures, and disruption and inefficiencies related to the aforementioned and the need to re-sequence construction activities. The impacts were also due to additional anticipated craft labor associated with more complex piping and other construction activities identified as we achieved further completion of production engineering. We have submitted a request for equitable adjustment to our customer, the U.S. Navy, to extend our project schedules and recover the increased forecast costs associated with the impacts of COVID-19; however, we can provide no assurances that we will be successful recovering these costs. Our forecasts at December 31, 2020 do not reflect potential future benefits, if any, from the favorable resolution of the request for equitable adjustment. Our forecasts reflect minimal craft labor productivity improvements from the first vessel to each follow-on vessel. At December 31, 2020, the projects were at varying stages of completion ranging from approximately 10% to 60% and are forecast to be completed at varying dates from 2022 through 2024, subject to the potential schedule impacts referenced above. The first three vessels were in a loss position at December 31, 2020 and our reserve for estimated losses was $3.2 million. The last two vessels were approximately break-even. If future craft labor productivity and subcontractor costs differ from our current estimates, piping or other construction activities are determined to be more complex than anticipated upon finalization of production engineering, we are unable to achieve our progress estimates or our schedules are further extended, the projects would experience further losses. See “Other Project Matters” below for further discussion of our towing, salvage and rescue ship projects.
|
|
•
|
Harbor Tug Projects – Negative impact for 2020 of $1.0 million resulting from increased forecast costs for our final two (ninth and tenth) harbor tug projects in our Jennings Yard, primarily associated with increased craft labor and subcontracted services costs and extensions of schedules. The impacts were primarily due to lower than anticipated craft labor productivity and progress on the projects resulting from the wind down of the Jennings Yard in connection with its closure in the fourth quarter 2020 and the impacts of COVID-19 associated primarily with physical distancing measures. The ninth vessel was completed in the fourth quarter 2020 and the tenth vessel was completed in January 2021.
|
|
•
|
Forty-Vehicle Ferry Projects – Negative impact for 2020 of $7.2 million resulting from increased forecast costs and forecast liquidated damages for our two forty-vehicle ferry projects ($6.2 million for the first vessel and $1.0 million for the second vessel), primarily associated with increased craft labor and material costs and extensions of schedules. The impacts were primarily due to lower than anticipated craft labor productivity and progress on the projects resulting from the current and forecasted impacts of COVID-19 and additional factors specific to each vessel as described further below:
|
|
-
|
Second Forty-Vehicle Ferry Project (see discussion of first vessel below) – The impacts for the second vessel were also due to construction rework and disruptions caused by structural design deficiencies for the vessel, which resulted in deflection issues within the plating of the vessel. We believe the impacts of the design deficiencies should be the responsibility of the customer. Accordingly, we will be submitting a claim to our customer to extend our project schedules and recover the increased forecast costs associated with the impacts of the design deficiencies; however, we can provide no assurances that we will be successful recovering these costs. Our forecast at December 31, 2020 does not reflect potential future benefits, if any, from the favorable resolution of the claim. At December 31, 2020, the second vessel was approximately 80% complete and is forecast to be completed in the second quarter 2021.
|
|
-
|
First Forty-Vehicle Ferry Project – The impacts for the first vessel were also due to construction rework, including reconstruction of previously completed portions of the vessel, resulting from the determination that portions of the vessel structure were outside of acceptable tolerance levels. The previous construction activities were performed by our former Fabrication Division prior to transferring management and project execution responsibility of the vessels to our Shipyard Division in the first quarter 2020 as discussed further in Note 10. The impacts were also due to the determination that construction of a new hull for the vessel is the most appropriate course of action as further discussed below.
|
During the third quarter 2020, the first vessel was damaged by an overhead crane, which disengaged from its tracks, and landed on the hull that was under construction. As a result of this damage to the hull, coupled with prior rework on the vessel, and associated concerns regarding the acceptable tolerance levels of the hull, in October 2020 our customer issued a rejection letter indicating that they would not accept a reconstructed hull, and requested the fabrication of a new hull. Accordingly, we ceased construction activities on the vessel as we evaluated our options, including remediation actions that could potentially be taken in lieu of fabricating a new hull. We also began discussions with our insurer regarding the impacts of the crane incident and the coverage that would apply to any cost increases for remediation actions or the fabrication of a new hull. Based on our preliminary estimates, we believed the incremental forecast costs resulting from the aforementioned could range from $1.0 million to $4.0 million (before consideration of insurance coverage), with such range of cost being highly dependent on the course of action ultimately taken with respect to the hull, which ranged from remediation actions to repair the hull to the fabrication of a new hull. Further, the ultimate cost to us was dependent upon any insurance proceeds received in connection with the crane incident. Due to the uncertainty with respect to the corrective actions that potentially could be taken regarding the hull and any insurance coverage that would apply, we were unable to estimate the amount we would likely incur from the crane incident. Accordingly, at September 30, 2020, we accrued our deductible of $0.1 million associated with our insurance coverage, representing the minimum amount we would incur for the crane incident. However, we have now determined that fabrication of a new hull is the most appropriate course of action due to, among other things, quality and cost uncertainties associated with repairing the hull, resulting in an increase in forecast costs of $4.1 million (included in the above referenced impacts for the year), inclusive of insurance proceeds, which were not material. We have ceased all work on the vessel and are in discussions with the customer regarding a path forward for recommencement of construction of the vessel.
We have also determined that the structural design deficiencies identified for the second vessel are applicable to the first vessel, which contributed to the aforementioned rework and construction challenges experienced on the first vessel. We will be submitting a claim to our customer to extend our project schedules and recover the increased costs associated with the impacts of the design deficiencies; however, we can provide no assurances that we will be successful recovering these costs. Our forecast at December 31, 2020 does not reflect potential future benefits, if any, from the favorable resolution of the claim. The completion date of the first vessel is uncertain due to the ongoing discussions with the customer; however, we currently do not anticipate completion in 2021.
The projects were in a loss position at December 31, 2020 and our reserve for estimated losses was $4.8 million. If future craft labor productivity and subcontractor costs differ from our current estimates, we are unable to achieve our progress estimates, our schedules are further extended or the projects incur additional schedule liquidated damages, the projects would experience further losses. We would also experience further losses if we were to incur further unanticipated costs associated with the design deficiencies, including fabrication of the new hull for the first vessel.
|
•
|
Seventy-Vehicle Ferry Project – Negative impact for 2020 of $1.1 million resulting from increased forecast costs for our seventy-vehicle ferry project, primarily associated with increased craft labor and subcontracted services costs and extensions of schedule. The impacts were primarily due to lower than anticipated craft labor productivity and progress on the projects resulting from the current and forecasted impacts of COVID-19 and our inability to achieve previously anticipated improvements in productivity. The impacts were also due to additional anticipated craft labor associated with more complex piping and other construction activities identified as we achieved further completion of production engineering. At December 31, 2020, the vessel was approximately 55% complete and is forecast to be completed in the fourth quarter 2021. The project was in a loss position at December 31, 2020 and our reserve for estimated losses was $0.5 million. If future craft labor productivity and subcontractor costs differ from our current estimates, piping or other construction activities are determined to be more complex than anticipated upon finalization of production engineering, we are unable to achieve our progress estimates, our schedules are further extended or the project incurs schedule liquidated damages, the project would experience further losses.
|
|
•
|
Research Vessel Projects – As discussed further below, we agreed to a change order with our customer for our research vessel projects that, among other things, provided for the customer’s assumption of responsibility for production engineering for the project. Further, we made a collective decision with our customer to delay construction activities on the projects until production engineering achieves a satisfactory level of completion to limit the impacts on construction, including disruption and rework. These construction delays are expected to continue in the near term due to production engineering delays experienced by our customer’s engineering subcontractor as a result of COVID-19. We are currently working collaboratively with the customer to identify opportunities to commence construction activities in advance of full completion of production engineering to minimize the schedule impacts to the projects. Based on our current forecast cost to complete the projects, the change order and collaborative nature of our discussions with the customer, we are not forecasting losses on the projects. However, as discussed further below, we are continuing to recognize revenue equal to costs on the projects until we are able to reasonably estimate the amount of gross profit, if any, expected to be realized on the projects. We anticipate being able to make such an estimate upon substantial completion of production engineering. If the projects experience further delays associated with production engineering or other matters, we are unable to achieve our progress estimates, piping or other construction activities are determined to be more complex than anticipated upon finalization of production engineering, our schedules are further extended or the projects incur schedule liquidated damages, future craft labor productivity and subcontractor costs differ from our current estimates, or we are unable to recover the costs of any of the aforementioned from our customer, the projects would experience losses.
|
Fabrication & Services Division
|
•
|
Jacket and Deck Project – Positive impact for 2020 of $1.2 million resulting from reduced forecast costs and increased contract price for our jacket and deck project, primarily associated with reduced subcontracted services costs, approved change orders and incentives. The impacts were primarily due to favorable resolution of customer and subcontractor change orders and realization of project incentives. At December 31, 2020, the project was complete.
|
|
•
|
Paddlewheel Riverboat and Subsea Components Projects – Positive impact for 2020 of $1.5 million resulting from reduced forecast costs and increased contract price for our paddlewheel riverboat and subsea components projects, primarily associated with reduced craft labor and subcontracted services costs and approved change orders. The impacts were primarily due to better than anticipated labor productivity and favorable resolution of customer and subcontractor change orders. At December 31, 2020, both projects were complete.
|
Changes in Estimates for 2019 – For 2019, significant changes in estimated margins on projects negatively impacted operating results for our Shipyard Division by $12.3 million and negatively impacted operating results for our Fabrication & Services Division by $4.9 million. The changes in estimates were associated with the following:
Shipyard Division
|
•
|
Harbor Tug Projects – Negative impact for 2019 of $4.9 million resulting from increased forecast costs and forecast liquidated damages for our harbor tug projects, primarily associated with increased craft labor, subcontracted services costs and extensions of schedule. The impacts were primarily due to lower than anticipated craft labor productivity and progress resulting from limitations in craft labor availability and the required use of contract labor in lieu of direct hire labor, the need to supplement and re-perform work for an under-performing paint subcontractor, higher than anticipated costs for paint scopes that were assumed by us from our paint subcontractor, higher cost estimates from our electrical and instrumentation subcontractor, our inability to achieve previously anticipated labor productivity improvements, and expectations of future labor productivity. The projects were in a loss position at December 31, 2019 and our reserve for estimated losses was $1.6 million. See “Changes in Estimates for 2020” above for further discussion of the status of these projects.
|
|
•
|
Forty-Vehicle Ferry Projects – Negative impact for 2019 of $5.1 million resulting from increased forecast costs and forecast liquidated damages for our two forty-vehicle ferry projects, primarily associated with increased craft labor and subcontracted services and materials costs. The impacts were primarily due to greater than anticipated rework, lower than anticipated productivity experienced primarily during the fourth quarter 2019, and our expectations of future labor productivity. The projects were in a loss position at December 31, 2019 and our reserve for estimated losses was $3.0 million. See “Changes in Estimates for 2020” above for further discussion of the status of these projects.
|
|
•
|
Ice-Breaker Tug Project – Negative impact for 2019 of $1.5 million resulting from increased forecast costs for our ice-breaker tug project, primarily associated with increased craft labor, subcontracted services costs and extension of schedule. The impacts were primarily due to construction rework and disruption and lower than anticipated craft labor productivity and progress on the project resulting from incomplete and deficient subcontracted production engineering, higher cost estimates from our various subcontractors, difficulties encountered to launch the vessel, and anticipated higher costs to deliver the vessel. The project was in a loss position at December 31, 2019 and our reserve for estimated losses was $0.1 million. At December 31, 2020, the project was complete.
|
|
•
|
Research Vessel Projects – Negative impact for 2019 of $0.8 million resulting from the reversal of gross profit recognized prior to 2019 for our three research vessel projects. The projects experienced difficulties with subcontracted production engineering, due in part to vessel size constraints and complexities associated with vessel functionality, which resulted in incomplete and deficient production engineering and construction delays, disruption and rework. As a result, we made a collective decision with our customer to delay construction activities on the projects until production engineering achieves a satisfactory level of completion to limit further impacts on construction, including disruption and rework. In addition, we agreed to a change order with the customer that included the following:
|
|
-
|
The replacement of the current subcontracted production engineering firm with a different engineering subcontractor that was contracted directly by the customer;
|
|
-
|
Extensions of the schedule liquidated damages dates for the projects; and
|
|
-
|
Increases in project price for the contracts to account for the estimated cost impacts of the production engineering and construction delays.
|
Based on our forecast cost to complete the projects, the change order and collaborative nature of our discussions with the customer, we are not forecasting losses on the projects. However, due to uncertainties with respect to the timing of completion of production engineering and the potential impacts on our construction schedules and costs, as well as ongoing discussions with the customer, we are unable to reasonably estimate the amount of gross profit, if any, that will ultimately be realized on the projects. Accordingly, during the fourth quarter 2019 we reversed all previously recognized gross profit on the projects (including the reversal of $2.5 million of gross profit that was recognized prior to the fourth quarter 2019) and are recognizing revenue equal to costs on the projects until we are able to reasonably estimate the amount of gross profit, if any, expected to be realized on the projects. See “Changes in Estimates for 2020” above for further discussion of the status of these projects.
Fabrication & Services Division
|
•
|
Paddle Wheel River Boat Project – Negative impact for 2019 of $1.3 million resulting from increased forecast costs for our paddle wheel river boat project, primarily associated with increased craft labor costs. The impacts were primarily due to difficulties encountered in commissioning the vessel and the need to accelerate our schedule, including performing out of sequence work scopes, to enable subcontracted works scopes to commence and mitigate the schedule and cost impacts of delaying the subcontracted work scopes. The project was in a loss position at December 31, 2019 and our reserve for estimated losses was $0.2 million. At December 31, 2020, the project was complete.
|
|
•
|
Jacket and Deck Project – Negative impact for 2019 of $2.0 million resulting from increased forecast costs and forecast liquidated damages for our jacket and deck project, primarily associated with increased subcontracted services costs and extensions of schedule. The impacts were primarily due to higher than anticipated cost estimates from our commissioning subcontractors and delays associated with customer related directives. The project was in a loss position at December 31, 2019 and our reserve for estimated losses was $1.1 million. At December 31, 2020, the project was complete.
|
|
•
|
Subsea Components Project – Negative impact for 2019 of $1.6 million resulting from increased forecast costs and liquidated damages for our subsea components project, primarily associated with increased craft labor, subcontracted services and materials costs and extensions of schedule. The impacts were primarily due to additional craft labor, materials costs and subcontracted services costs and support resulting from stringent welding procedure requirements and customer specifications. The project was in a loss position at December 31, 2019 and our reserve for estimated losses was $0.2 million. At December 31, 2020, the project was complete.
|
Changes in estimates for 2018 – For 2018, significant changes in estimated margins on projects negatively impacted operating results for our Shipyard Division by $2.4 million and negatively impacted operating results of our Fabrication & Services Division by $6.7 million. The changes in estimates were associated with the following:
Shipyard Division
|
•
|
Harbor Tug Projects – Negative impact for 2018 of $6.7 million resulting from increased forecast costs and liquidated damages for our harbor tug projects, primarily associated with craft labor costs and extensions of schedule. The impacts were primarily due to lower than anticipated craft labor productivity related to pipe installation and testing. See “Changes in Estimates for 2020” above for further discussion of the status of these projects.
|
Fabrication & Services Division
|
•
|
Petrochemical Modules Project – Negative impact for 2018 of $2.4 million resulting from increased forecast costs for our petrochemical modules project, primarily associated with increased subcontracted services costs. The impacts were primarily due to higher cost estimates from our insulation and other subcontractors. At December 31, 2020, the project was complete.
|
Other Project Matters
Hurricane Laura – In August 2020, Hurricane Laura made landfall as a high-end Category 4 hurricane in Lake Charles, Louisiana, where its high winds and flooding caused significant damage throughout the region. At our Lake Charles Yard, Hurricane Laura primarily damaged drydocks, warehouses, bulkheads and our ninth harbor tug project which was nearing completion and subsequently completed in the fourth quarter 2020. As a result, during 2020, we recorded charges of $1.3 million related to deductibles associated with our builder’s risk, equipment, property and marine liability insurance coverages, and our preliminary estimates of cost associated with uninsurable damage, primarily for bulkheads. The charges are included in other (income) expense, net on our Statement of Operations.
Project Tariffs – Certain imported materials used, or forecast to be used, for our projects are currently subject to existing, new or increased tariffs or duties. We believe such amounts, if incurred, are recoverable from our customers under the contractual provisions of our contracts; however, we can provide no assurances that we will successfully recover such amounts.
Towing, Salvage and Rescue Ship Project Change Order – Our contract for the construction of our five towing, salvage and rescue ships contains options which grant our customer, the U.S. Navy, the right, if exercised, for the construction of three additional vessels at contracted prices. During the first quarter 2021, the U.S. Navy determined it would not exercise the three remaining options under our contract. In connection therewith, we agreed to a change order of $13.1 million with the U.S. Navy to facilitate the transfer of technology, plans and know-how to the customer to enable it to contract with other contractors for the construction of additional vessels. The majority of the change order will be included within contract price for our existing vessel projects and recognized as revenue on a percentage-of-completion basis as the projects progress and the remainder will be recognized as revenue as we facilitate the transfer of the technology, plans and know-how during 2021.
|