Quarterly report pursuant to Section 13 or 15(d)

REVENUE, CONTRACT ASSETS AND LIABILITIES AND OTHER CONTRACT MATTERS

v3.23.3
REVENUE, CONTRACT ASSETS AND LIABILITIES AND OTHER CONTRACT MATTERS
9 Months Ended
Sep. 30, 2023
Revenue from Contract with Customer [Abstract]  
REVENUE, CONTRACT ASSETS AND LIABILITIES AND OTHER CONTRACT MATTERS

2. REVENUE, CONTRACT ASSETS AND LIABILITIES AND OTHER CONTRACT MATTERS

As discussed in Note 1, we recognize revenue from our contracts in accordance with Topic 606. Summarized below are required disclosures under Topic 606 and other relevant guidance.

Disaggregation of Revenue

The following tables summarize revenue for each of our operating segments, disaggregated by contract type and duration, for the three and nine months ended September 30, 2023 and 2022 (in thousands):

 

 

 

Three Months Ended September 30, 2023

 

 

 

Services

 

 

Fabrication

 

 

Shipyard

 

 

Eliminations

 

 

Total

 

Fixed-price and unit-rate

 

$

557

 

 

$

12,185

 

 

$

(32,702

)

 

$

(20

)

 

$

(19,980

)

T&M and cost-reimbursable

 

 

21,086

 

 

 

2,794

 

 

 

 

 

 

 

 

 

23,880

 

Other

 

 

1,333

 

 

 

 

 

 

 

 

 

(210

)

 

 

1,123

 

Total

 

$

22,976

 

 

$

14,979

 

 

$

(32,702

)

 

$

(230

)

 

$

5,023

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Long-term

 

$

557

 

 

$

13,043

 

 

$

(32,702

)

 

$

(20

)

 

$

(19,122

)

Short-term

 

 

22,419

 

 

 

1,936

 

 

 

 

 

 

(210

)

 

 

24,145

 

Total

 

$

22,976

 

 

$

14,979

 

 

$

(32,702

)

 

$

(230

)

 

$

5,023

 

 

 

 

Three Months Ended September 30, 2022

 

 

 

Services

 

 

Fabrication

 

 

Shipyard

 

 

Eliminations

 

 

Total

 

Fixed-price and unit-rate

 

$

986

 

 

$

11,410

 

 

$

1,849

 

 

$

(1

)

 

$

14,244

 

T&M and cost-reimbursable

 

 

20,937

 

 

 

2,373

 

 

 

 

 

 

 

 

 

23,310

 

Other

 

 

646

 

 

 

1,646

 

 

 

 

 

 

(253

)

 

 

2,039

 

Total

 

$

22,569

 

 

$

15,429

 

 

$

1,849

 

 

$

(254

)

 

$

39,593

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Long-term

 

$

986

 

 

$

14,078

 

 

$

1,849

 

 

$

(1

)

 

$

16,912

 

Short-term

 

 

21,583

 

 

 

1,351

 

 

 

 

 

 

(253

)

 

 

22,681

 

Total

 

$

22,569

 

 

$

15,429

 

 

$

1,849

 

 

$

(254

)

 

$

39,593

 

 

 

 

Nine Months Ended September 30, 2023

 

 

 

Services

 

 

Fabrication

 

 

Shipyard

 

 

Eliminations

 

 

Total

 

Fixed-price and unit-rate

 

$

1,356

 

 

$

37,773

 

 

$

(30,973

)

 

$

(30

)

 

$

8,126

 

T&M and cost-reimbursable

 

 

64,456

 

 

 

31,609

 

 

 

 

 

 

 

 

 

96,065

 

Other

 

 

3,221

 

 

 

 

 

 

 

 

 

(895

)

 

 

2,326

 

Total

 

$

69,033

 

 

$

69,382

 

 

$

(30,973

)

 

$

(925

)

 

$

106,517

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Long-term

 

$

1,356

 

 

$

65,259

 

 

$

(30,973

)

 

$

(30

)

 

$

35,612

 

Short-term

 

 

67,677

 

 

 

4,123

 

 

 

 

 

 

(895

)

 

 

70,905

 

Total

 

$

69,033

 

 

$

69,382

 

 

$

(30,973

)

 

$

(925

)

 

$

106,517

 

 

 

 

Nine Months Ended September 30, 2022

 

 

 

Services

 

 

Fabrication

 

 

Shipyard

 

 

Eliminations

 

 

Total

 

Fixed-price and unit-rate

 

$

3,557

 

 

$

25,651

 

 

$

7,314

 

 

$

(7

)

 

$

36,515

 

T&M and cost-reimbursable

 

 

59,903

 

 

 

3,588

 

 

 

 

 

 

 

 

 

63,491

 

Other

 

 

1,953

 

 

 

2,646

 

 

 

 

 

 

(424

)

 

 

4,175

 

Total

 

$

65,413

 

 

$

31,885

 

 

$

7,314

 

 

$

(431

)

 

$

104,181

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Long-term

 

$

3,557

 

 

$

29,319

 

 

$

7,314

 

 

$

(7

)

 

$

40,183

 

Short-term

 

 

61,856

 

 

 

2,566

 

 

 

 

 

 

(424

)

 

 

63,998

 

Total

 

$

65,413

 

 

$

31,885

 

 

$

7,314

 

 

$

(431

)

 

$

104,181

 

 

Future Performance Obligations

The following table summarizes our remaining performance obligations, disaggregated by operating segment and contract type, at September 30, 2023 (in thousands):

 

 

 

September 30, 2023

 

 

 

Services

 

 

Fabrication

 

 

Shipyard

 

 

Total

 

Fixed-price and unit-rate

 

$

867

 

 

$

10,033

 

 

$

726

 

 

$

11,626

 

T&M and cost-reimbursable(1)

 

 

 

 

 

1,474

 

 

 

 

 

 

1,474

 

Total(2)

 

$

867

 

 

$

11,507

 

 

$

726

 

 

$

13,100

 

 

(1)
In February 2023, we received direction from our customer to suspend all activities on our offshore jackets project for our Fabrication Division, and in July 2023, the customer cancelled the contract. Accordingly, during the second quarter 2023, our performance obligations were reduced by $76.1 million to reflect the estimated revenue amount that will not be recognized due to the cancellation. See “Other Operating and Project Matters” below for further discussion of the project cancellation.
(2)
Based on our current estimates we expect to recognize revenue of approximately $12.6 million and $0.5 million for the remainder of 2023 and 2024, respectively, associated with our performance obligations at September 30, 2023. Certain factors and circumstances could result in changes in the timing of recognition of our performance obligations as revenue and the amounts ultimately recognized.

Contracts Assets and Liabilities

The timing of customer invoicing and recognition of revenue using the POC method may occur at different times. Customer invoicing is generally dependent upon contractual billing terms, which could provide for customer payments in advance of performing the work, milestone billings based on the completion of certain phases of the work, or billings when services are provided. Revenue recognized in excess of amounts billed is reflected as contract assets on our Balance Sheet, or to the extent we have an unconditional right to the consideration, is reflected as contract receivables on our Balance Sheet. Amounts billed in excess of revenue recognized, and accrued contract losses, are reflected as contract liabilities on our Balance Sheet. Information with respect to contracts that were incomplete at September 30, 2023 and December 31, 2022, is as follows (in thousands):

 

 

 

September 30,

 

 

December 31,

 

 

 

2023

 

 

2022

 

Contract assets(1), (2)

 

$

4,305

 

 

$

4,839

 

Contract liabilities(3), (4), (5)

 

 

(3,534

)

 

 

(8,196

)

Contracts in progress, net

 

$

771

 

 

$

(3,357

)

 

(1)
The decrease in contract assets compared to December 31, 2022, was primarily due to decreased unbilled positions on our forty-vehicle ferry projects for our Shipyard Division, offset partially by increased unbilled positions on various projects for our Fabrication Division.
(2)
Contract assets at September 30, 2023 and December 31, 2022, excluded $3.8 million and $3.6 million, respectively, associated with revenue recognized in excess of amounts billed for which we have an unconditional right to the consideration. Such amounts are reflected within contract receivables.
(3)
The decrease in contract liabilities compared to December 31, 2022, was primarily due to a decrease in advance billings on our cancelled offshore jackets project for our Fabrication Division and accrued contract losses on our forty-vehicle ferry projects for our Shipyard Division. See “Future Performance Obligations” above for further discussion of the project cancellation.
(4)
Revenue recognized during the three months ended September 30, 2023 and 2022, related to amounts included in our contract liabilities balance at June 30, 2023 and 2022 was $1.1 million and $0.6 million, respectively. Revenue recognized during the nine months ended September 30, 2023 and 2022, related to amounts included in our contract liabilities balance at December 31, 2022 and 2021, was $6.2 million and $2.7 million, respectively.
(5)
Contract liabilities at September 30, 2023 and December 31, 2022, includes accrued contract losses of $0.4 million and $1.6 million, respectively. See “Changes in Project Estimates” below for further discussion of our accrued contract losses and Note 4 for discussion of the noncurrent contract liability associated with the resolution of our MPSV Litigation.

Allowance for Doubtful Accounts and Credit Losses

Our provision for bad debts and credit losses is included in other (income) expense, net on our Statement of Operations. For the three and nine months ended September 30, 2023, we recognized income of $0.2 million and $0.4 million, respectively, associated with revisions to our allowance for doubtful accounts and credit losses, and for the three and nine months ended September 30, 2022, changes were not significant. Our allowance for doubtful accounts and credit losses at September 30, 2023 was $0.2 million, and it was not significant at December 31, 2022. We recorded a $0.6 million increase to beginning accumulated deficit as of January 1, 2023, in connection with our adoption of ASU 2016-13. We had no significant write-offs or recoveries of previously recorded bad debts during the three or nine months ended September 30, 2023 or 2022. See “New Accounting Standards” in Note 1 for further discussion of our adoption of ASU 2016-13.

Variable Consideration

For the three and nine months ended September 30, 2023 and 2022, we had no material amounts in revenue related to unapproved change orders, claims or incentives, other than the amounts related to the resolution of our MPSV Litigation discussed further below. However, at September 30, 2023 and December 31, 2022, certain active projects within our Shipyard Division reflected a reduction to our estimated contract price for liquidated damages of $1.5 million and $1.4 million, respectively.

Changes in Project Estimates

We determine the impact of changes in estimated margins on projects for a given period by calculating the amount of revenue recognized in the period that would have been recognized in a prior period had such estimated margins been forecasted in the prior period. The total impact of changes in estimated margins for a project as disclosed on a quarterly basis may be different from the applicable year-to-date impact due to the application of the POC method and the changing progress of the project at each period end. Such impacts may also be different when a project is commenced and completed within the applicable year-to-date period but spans multiple quarters.

As a result of the resolution of our MPSV Litigation, we recorded a charge of $32.5 million during each of the three and nine months ended September 30, 2023. See Note 4 for further discussion of the resolution of our MPSV Litigation.

For each of the three and nine months ended September 30, 2023, significant changes in estimated margins on projects positively impacted operating results for our Fabrication Division by $0.7 million, and negatively impacted operating results for our Shipyard Division by $1.5 million and $2.3 million, respectively. For the three and nine months ended September 30, 2022, individual projects with significant changes in estimated margins did not have a material net impact on our operating results. The changes in estimates for the 2023 periods were associated with the following:

Fabrication Division

Various Projects – For each of the three and nine months ended September 30, 2023, our operating results were positively impacted by $0.7 million on projects, resulting primarily from increases in contract price due to favorable resolution of customer change orders.

Shipyard Division

Seventy-Vehicle Ferry Project – For the three and nine months ended September 30, 2023, our operating results were negatively impacted by $1.2 million and $1.8 million, respectively, for our seventy-vehicle ferry project, resulting primarily from increased materials and subcontracted services costs, duration related costs due to extensions of schedule and net reductions to contract price. The cost impacts were primarily due to delays in the receipt of certain equipment that required replacement and subcontractor delays. The contract price impacts were primarily due to a reduction related to the propeller blades replacement discussed further below, offset partially by increases due to favorable resolution of customer change orders and the customer’s agreement to forego a portion of previously forecasted liquidated damages.

As discussed in our previous quarterly filing, in connection with the delivery and commissioning of the vessel in the second quarter 2023, corrosion on the propeller blades was identified and the customer has determined that replacement of the propeller blades will be required. The customer has agreed to directly procure the new propeller blades and take responsibility for future installation of the blades once received. However, the customer believes we should bear the cost of the new propeller blades through a contract price reduction. We disagree with the customer given the fact that the customer specified the materials and equipment manufacturers to be used for the propulsion system and specified the cathodic protection to be used to mitigate corrosion. In light of the disagreement with the customer regarding who is responsible for the cost of the propeller blades, our forecasts at September 30, 2023, reflect a contract price reduction related to the estimated cost of the propeller blades. We are having ongoing discussions with the customer regarding who should bear final responsibility for the cost of the propeller blades.

At September 30, 2023, the vessel was substantially complete and has been delivered to the customer. We anticipate completion of commissioning activities and final sea trials to occur in the fourth quarter 2023 (previously the third quarter 2023, but was delayed due to the aforementioned impacts). At September 30, 2023, the project was in a loss position and our reserve for estimated losses was $0.1 million. If future subcontractor availability or costs differ from our current estimates, our schedule is further extended or we incur additional liquidated damages, we experience challenges during commissioning or sea trials for the vessel, or unanticipated warranty costs, the project would experience further delays and losses.

Forty-Vehicle Ferry Projects – During the second quarter 2023, we received final customer acceptance of one of the two forty-vehicle ferries that were under construction. For the three and nine months ended September 30, 2023, our operating results were negatively impacted by $0.3 million and $0.5 million, respectively, for our remaining forty-vehicle ferry project, resulting primarily from increased subcontracted services and duration related costs due to extensions of schedule, including forecast liquidated damages. The impacts were primarily due to delays in the receipt of certain equipment that required replacement and subcontractor delays. At September 30, 2023, the vessel was substantially complete, and as of the date of this Report, the ferry is in route for delivery to the customer. We anticipate completion of delivery, commissioning activities and final sea trials to occur in the fourth quarter 2023 (previously the third quarter 2023, but was delayed due to the aforementioned impacts). At September 30, 2023, the project was in a loss position and our reserve for estimated losses was $0.3 million.

As discussed in our 2022 Financial Statements, we have experienced rework, construction and commissioning challenges on the two ferries, resulting in forecast cost increases and liquidated damages and the previous need to fabricate a new hull for the remaining vessel. Accordingly, during 2021 we submitted claims to our customer, and subsequently filed a lawsuit, to extend our project schedules and recover the cost impacts of the design deficiencies. The customer denied all liability. Further, during the fourth quarter 2022 and early 2023, we received correspondence from our customer indicating that the new hull for the remaining ferry under construction was exhibiting deformation issues that are potentially beyond the customer’s desired tolerance levels. Our subsequent evaluation did not support the customer’s conclusions and we completed construction of the vessel as designed.

Our forecast costs and scheduled completion date for the remaining vessel are based on the current vessel design and reflect our best estimates; however, such estimates may be impacted by any future challenges with the vessel design deficiencies, including the final resolution of the aforementioned design and deformation issues in dispute. If future subcontractor availability or costs differ from our current estimates, our schedule is further extended or we incur additional liquidated damages, we experience challenges during delivery, commissioning or sea trails for the remaining vessel, or other challenges associated with the design deficiencies, including unanticipated warranty costs (for either vessel), and are unable to recover associated costs from our customer, or the customer rejects delivery and/or final acceptance of the remaining vessel due to the design dispute, the project would experience further delays and losses. Our forecasts at September 30, 2023 do not reflect potential future benefits, if any, from the favorable resolution of the aforementioned lawsuit and we can provide no assurance that we will be successful recovering previously incurred costs.

Other Operating and Project Matters

Hurricane Ida On August 29, 2021, Hurricane Ida made landfall near Houma, Louisiana as a high-end Category 4 hurricane, with high winds and heavy rains causing damage to buildings and equipment at our Houma Facilities and resulting in significant debris throughout the facility. Our insurance coverages in effect at the time of the storm generally specify coverage amounts for each of our buildings (including contents) and major equipment.

During the nine months ended September 30, 2023 and 2022, we received insurance payments of $2.2 million and $7.0 million, respectively, from our insurance carriers associated with interruptions to our operations and damage to buildings and equipment. In addition, we have received payments from our insurance carriers during other periods subsequent to the storm associated with interruptions to our operations and damage to buildings and equipment. Such payments are nonrefundable, and with respect to our buildings, represent the insurance carriers’ estimate of the damage to each building based on the estimated depreciated value of such buildings plus repair costs incurred by us in excess of such estimates for certain buildings. To the extent we incur further repair costs for a building in excess of the amounts received, we may receive additional insurance proceeds up to the limits of our insurance coverage for such building. The classification of insurance proceeds within our Statement of Cash Flows is based on our use or intended use of the proceeds. Proceeds used or intended to be used for repairs that are not deemed to be capital in nature, and proceeds associated with interruptions to our operations, are reflected within operating activities. Proceeds used or intended to be used for repairs that are deemed capital in nature, or proceeds in excess of anticipated repair costs, are reflected within investing activities.

The timing of payments from our insurance carriers have, and may continue to, differ from when we incur the applicable repair and cleanup costs, and accordingly, we have accounted for such differences in timing as follows:

To the extent we incurred repair costs in excess of insurance proceeds received to date, we recorded an insurance receivable when we believe such amounts are probable of recovery under our insurance policies.
To the extent we determined that damage to an asset resulted in a complete loss, we recorded an insurance receivable up to the impairments recognized when we believe such amounts are probable of recovery under our insurance policies.
To the extent proceeds received exceeded repair costs incurred to date, we recorded an insurance gain as we do not have an obligation to perform further repair activities. Charges will be recorded in future periods to the extent such proceeds received are used for future repair activities that are not deemed to be capital in nature.
Insurance deductibles, clean-up costs and uninsured losses have been expensed.

Based on the above, during the three months ended September 30, 2023 and 2022, and nine months ended September 30, 2023 and 2022, we recorded gains of $0.3 million (all related to our business interruption coverage), $1.3 million, $0.5 million (including $0.6 million related to our business interruption coverage) and $4.4 million, respectively, related to the net impact of insurance recoveries and costs associated with damage previously caused by Hurricane Ida. The gains are included in other (income) expense, net on our Statement of Operations and are reflected within our Fabrication Division. In addition, at September 30, 2023, we had total insurance receivables on our Balance Sheet of $0.1 million. We have finalized our restoration plans and are nearing completion of our repair efforts. We expect to incur future repair costs of approximately $0.5 million associated with previously received insurance payments for certain buildings and equipment. Further, we expect to incur future repair costs in excess of previously received insurance payments for certain buildings and equipment; however, we believe that recovery of insurance proceeds for such costs is probable.

In addition to damage to our Houma Facilities, the storm resulted in damage to one of our forty-vehicle ferry projects, the multi-purpose supply vessels (“MPSVs”) and associated equipment that remain in our possession and were subject to our previous MPSV Litigation, and certain bulkheads where the vessels were moored. We are continuing to evaluate the extent to which any damage was the result of third-party vessels that broke free from their mooring during the storm and struck the ferry, MPSVs and bulkheads. During the three months ended September 30, 2023, we recorded charges of $0.1 million, and during the nine months ended September 30, 2023 and 2022, we recorded charges of $0.4 million and $0.2 million, respectively, associated with damage previously caused by Hurricane Ida. See Note 4 for further discussion of the resolution of our MPSV Litigation.

Offshore Jackets Project – As discussed above, in February 2023, we received direction from our customer to suspend all activities on our offshore jackets project for our Fabrication Division, and in July 2023, the customer cancelled the contract. At September 30, 2023, we had $5.0 million of accounts receivable on our Balance Sheet related to the project and we expect such amounts to be paid in the fourth quarter 2023. We have received a payment guarantee bond as security for the remaining accounts receivable amounts.