Quarterly report pursuant to Section 13 or 15(d)

CONTRACTS RECEIVABLE

v2.4.0.6
CONTRACTS RECEIVABLE
9 Months Ended
Sep. 30, 2012
CONTRACTS RECEIVABLE

NOTE 2 – CONTRACTS RECEIVABLE

The principal customers of the Company include major and large independent oil and gas companies and their contractors. Of our contracts receivable balance at September 30, 2012, $68.2 million, or 74.3%, is for three customers.

On July 13, 2012, we received notice from our customer, Bluewater Industries (“Bluewater”), requesting (i) a slowdown of work on ATP Oil & Gas (UK) Limited’s (“ATP UK’s”) Cheviot project ordered pursuant to a master service contract between Bluewater and the Company (the “Contract”), and (ii) an amendment to the scheduled payment terms under the Contract. On August 16, 2012, we entered into a binding agreement (the “Agreement”) with Bluewater, an engineering consulting firm engaged by ATP UK to oversee the fabrication of the Cheviot project, to amend and restate the Contract and suspend the project. Among other things, the Agreement outlines the revised payment terms for the contracts receivable balance (the “Balance”) and the limitations on Bluewater’s ability to request an extended suspension of work. Specifically, Bluewater must pay $200,000 on or before the last day of each calendar month until February 28, 2013, with the remaining outstanding Balance due on or before March 31, 2013. In addition, if Bluewater has fully paid the Balance on or prior to March 31, 2013, Bluewater has the option to extend the suspension of work on the Cheviot project to June 30, 2013, after which Bluewater will have no further rights to request a suspension of work. If Bluewater fails to make timely payments pursuant to the revised payment plan, we have the right to terminate the Contract, and we will continue to retain title to any project deliverables.

On August 17, 2012, ATP Oil & Gas, Inc. (“ATP”), the parent company of ATP UK, filed a voluntary petition for relief under Chapter 11 of the United States Bankruptcy Code. Although ATP is not our customer and ATP UK is not a party to the bankruptcy, we believe ATP has historically financed the operations of its subsidiaries, including ATP UK. We believe Bluewater’s ability to continue to meet its obligations under the Agreement, including payment of the outstanding Balance on or before March 31, 2013, largely depends on ATP UK’s ability to fund the Cheviot project.

As of September 30, 2012, $56.7 million has been billed on the Cheviot project and its outstanding contracts receivable balance was approximately $32.1 million. All installments due under the Agreement have been paid to-date. Our work on the Cheviot project is suspended and will remain suspended until the outstanding Balance is paid in full. Although it is too early to determine the ultimate outcome of the impact of ATP’s bankruptcy on the Cheviot project, in the event Bluewater is unable to comply with its obligations under the Agreement and the Contract is terminated, we will retain title to all project deliverables. Given the suspension of the project and the uncertainty around ATP’s bankruptcy, events in the future could change the timing and amount of the remaining contract price we ultimately recover.

On January 14, 2011, we entered into an agreement with one of our customers regarding the collection of an $11.0 million retainage balance on a completed contract. As consideration to extend payment, we agreed to receive $12.5 million, payable in twenty equal monthly installments beginning on June 30, 2011. Scheduled payments have been received through September 30, 2012 and the balance outstanding as of September 30, 2012 is $2.5 million, which is scheduled to be collected through January 2013.